ATC Pirbright

This critical project involved the replacement of 10 boilers across 5 accommodation blocks within a tight timescale prior to recruits returning to the barracks. The high efficiency, low NOX boilers will provide heat to these accommodation blocks for the next 15-20 years whilst reducing running costs and emissions.

According to an Amey press release completing the project early has saved the Army around £45,000 in temporary boiler hire costs.

 

Description

During the height of lockdown due to the COVID-19 pandemic a team from BJF Group’s Facilities Management Division completed a significant and important project at ATC Pirbright for Amey Defence on behalf of the Ministry of Defence.

Division

Facilities Management

Project Length

4 weeks

John Riley, Regional Director – Amey

“I just wanted to give some well-deserved recognition to your team at Pirbright. The barracks was pretty much empty when the Army suspended training.  This gave us a gap in which to replace 10 boilers in five accommodation blocks, two per block.  The job was finished ahead of time saving the use of temporary boilers.  The BJF team did a great job! Thank you!”

Why BJF?
We work in partnership with our clients to make their buildings better, safer and greener by designing, building, maintaining and refurbishing their spaces, and ensuring the most efficient functioning building services that bring those spaces to life.
Find out more
Call us 01622 266266

Delivering nationwide to private and public sector clients.

Contact